Padma bridge’s 35th span to be installed today...

Dhaka, Friday   27 November 2020

Padma bridge’s 35th span to be installed today

 Munshiganj Correspondent daily-bangladesh.com

 Published: 10:35 AM, 31 October 2020   Updated: 01:05 PM, 31 October 2020

Photo: Daily Bangladesh

Photo: Daily Bangladesh

The 35th span of the Padma Multi-Purpose Bridge would be installed on Saturday. The 2-B span is to be placed at pillars 8 and 9 at the Mawa end of the bridge in Munshiganj. After installing the 150-meter long span, 5,250 meters of the Padma Bridge will become visible. 

Executive Engineer and Project Manager (Main Bridge) Dewan Md Abdul Quader confirmed the information. 

He said that the span was due to be placed on Friday. But, the water level is very low in the spot where the span is to be placed and so the vessel carrying the crane that will lift the span, cannot reach there. Dredging and silt removal is being carried out to increase the river's navigability at the spot, Md Abdul Quader added. 

Earlier, officials of the Padma Bridge project said that all 41 spans will be installed on the Multi-Purpose Bridge by the next two months. 

“A total 41 spans will become visible on the bridge together in December, as the pace of work is going fast with maintaining proper health guidelines during the coronavirus pandemic,” Project Director of Padma Bridge Md Shafiqul Islam told BSS on October 18. 

According to project details, the 36th span of the bridge will be placed on November 4, the 37th span on November 11, 38th on November 16, 39th on November 23 and the 40th on December 2. Besides, the last and 41st span of the Padma Bridge will set up on the 12th and 13th piers of the bridge on December 10, it said. 

The Padma Bridge is the largest construction infrastructure since the independence of Bangladesh, which was initiated by Prime Minister Sheikh Hasina. The construction work began in December 2014 with own fund.

The construction of the main bridge is being made by China Major Bridge Engineering Company (MBEC), a Chinese contractor Company, and the river management is being done by Sino Hydro Corporation of China.

The 6.15 km long bridge will have two segments over which road and railways will be set up. 

DailyBangladesh/AN